{"id":69434,"date":"2016-04-08T13:15:28","date_gmt":"2016-04-08T13:15:28","guid":{"rendered":"http:\/\/mostafa.openonline.co.uk\/?guid=4b0c644c0e802b0ca12f7516b3ed60b0"},"modified":"2016-04-08T13:15:28","modified_gmt":"2016-04-08T13:15:28","slug":"press-release-planned-road-works-in-west-midlands-weekly-summary-for-monday-11-april-2016-to-sunday-17-april-2016","status":"publish","type":"post","link":"https:\/\/mostafa.openonline.co.uk\/?p=69434","title":{"rendered":"Press release: Planned road works in West Midlands: weekly summary for Monday 11 April 2016 to Sunday 17 April 2016"},"content":{"rendered":"<div class=\"govspeak\">\n<p>The following summary of planned new and ongoing road improvements over the coming week is correct as of 8 April 2016 but could be subject to change due to weather conditions or unforeseen circumstances. All our improvement work is carried out with the aim of causing as little disruption as possible.<\/p>\n<h2 id=\"a38--weeford-island-entry-slip-road-column-installation\">A38 \u2013 Weeford Island entry slip road: column installation<\/h2>\n<p>The northbound entry slip road will be closed overnight for one night from 8.30pm 12 April until 4am the following morning (13 April). A diversion route will be clearly signposted.<\/p>\n<h2 id=\"a49--dinmore-hill-road-layout-and-footpath-improvements\">A49 \u2013 Dinmore Hill: Road layout and footpath improvements<\/h2>\n<p>The carriageway will be closed in overnight in both directions between 10pm and 7am from 11 April until 15 April. A diversion route will be clearly signposted.<\/p>\n<h2 id=\"a5--churchbridge-to-washbrook-lane-footway-widening\">A5 \u2013 Churchbridge to Washbrook Lane: footway widening<\/h2>\n<p>The eastbound and westbound carriageway will be closed overnight between 8pm and 6am from 11 April until 17 April. A diversion route will be clearly signposted.<\/p>\n<h2 id=\"a50--meir-tunnel-to-blyth-bridge-signing-and-white-lining\">A50 \u2013 Meir Tunnel to Blyth Bridge: signing and white lining<\/h2>\n<p>The westbound carriageway will be closed overnight between 8pm and 5.30am from 11 April until 15 April. A diversion route will be clearly signposted.<\/p>\n<h2 id=\"m42--junction-9-vrs-scheme\">M42 \u2013 junction 9: vrs scheme<\/h2>\n<p>The northbound carriageway will be closed overnight between 9pm and 6am from 11 April until 17 April. A diversion route will be clearly signposted.<\/p>\n<h2 id=\"m42--junction-9-vrs-scheme-1\">M42 \u2013 junction 9: vrs scheme<\/h2>\n<p>The southbound carriageway will be closed overnight between 9pm and 6am from 11th April until 17 April. A diversion route will be clearly signposted.<\/p>\n<h2 id=\"m42--junction-5-to-junction-4-repairs-to-message-signs\">M42 \u2013 junction 5 to junction 4: repairs to message signs<\/h2>\n<p>The southbound carriageway will be closed overnight for one night from 10pm 12 April until 5am the following morning (13 April). A diversion route will be clearly signposted.<\/p>\n<h2 id=\"m50---junction-3-entry-and-exit-slip-roads-litter-clearance\">M50 &#8211; junction 3 entry and exit slip roads: litter clearance<\/h2>\n<p>The eastbound slip roads will be closed overnight for one night from 9pm 11 April until 5am the following morning (12 April). A diversion route will be clearly signposted.<\/p>\n<h2 id=\"m5-junction-5-northbound-exit-slip-road-all-lanes-running-scheme\">M5 junction 5 northbound exit slip road: all lanes running scheme<\/h2>\n<p>The northbound exit slip road will be closed overnight between 8pm and 6am on 11 April. A diversion route will be clearly signposted.<\/p>\n<h2 id=\"m5-junction-5-southbound-exit-slip-road-all-lanes-running-scheme\">M5 junction 5 southbound exit slip road: all lanes running scheme<\/h2>\n<p>The southbound exit slip road will be closed overnight between 8pm and 6am on 12, 14 and 15 April. A diversion route will be clearly signposted.<\/p>\n<h2 id=\"m5-junction-6-southbound-exit-slip-road-all-lanes-running-scheme\">M5 junction 6 southbound exit slip road: all lanes running scheme<\/h2>\n<p>The southbound exit slip road will be closed overnight between 8pm and 6am on 12 and 13 April. A diversion route will be clearly signposted.<\/p>\n<h2 id=\"m54--junction-2-to-junction-3-including-slip-roads-filter-drain-renewals\">M54 \u2013 junction 2 to junction 3 including slip roads: filter drain renewals<\/h2>\n<p>The carriageway including the entry and exit slip roads will be closed in both directions overnight between 11.30pm and 6am from 11 April until 15 April. Please note the slips will not be closed in both directions at the same time. A diversion route will be clearly signposted.<\/p>\n<h2 id=\"m54--junction-1-entry-slip-road-filter-drain-renewals\">M54 \u2013 junction 1 entry slip road: filter drain renewals<\/h2>\n<p>The eastbound entry slip road will be overnight between 8pm and 6am from 11 April until 14 April.  A diversion route will be clearly signposted.<\/p>\n<h2 id=\"m54--junction-3-to-junction-4-carriageway-resurfacing\">M54 \u2013 junction 3 to junction 4: carriageway resurfacing<\/h2>\n<p>The westbound carriageway will be closed overnight for one night from 9pm 11 April until 6am the following morning (12 April). A diversion route will be clearly signposted.<\/p>\n<h2 id=\"m54--junction-4-exit-slip-road-installation-of-new-electricity-supply\">M54 \u2013 junction 4 exit slip road: installation of new electricity supply<\/h2>\n<p>The westbound exit slip road will be closed overnight for one night from 7pm 13 April until 6am the following morning (14 April). A diversion route will be clearly signposted.<\/p>\n<h2 id=\"m6---junction-5-entry-slip-bridge-repairs\">M6 &#8211; junction 5 entry slip: bridge repairs<\/h2>\n<p>There will be a full 24hour southbound entry slip road closure from 18 January ongoing until 6am 30 June. A diversion route will be clearly signposted.<\/p>\n<h2 id=\"m6--junction-9-exit-and-entry-slip-road-carriageway-works\">M6 \u2013 junction 9 exit and entry slip road: carriageway works<\/h2>\n<p>The southbound and southbound entry and exit slip roads will be closed overnight between 9pm and 5am from 11 April until 15 April. A diversion route will be clearly signposted.<\/p>\n<h2 id=\"m6--junction-13-entry-slip-road-electrical-works\">M6 \u2013 junction 13 entry slip road: electrical works<\/h2>\n<p>The southbound entry slip road will be closed overnight for one night from 8pm 12 April until 6am the following morning (13 April). A diversion route will be clearly signposted.<\/p>\n<h2 id=\"m6--junction-11-entry-slip-road-electrical-works\">M6 \u2013 junction 11 entry slip road: electrical works<\/h2>\n<p>The northbound entry slip road will be closed overnight for one night from 8pm 13 April until 6am the following morning (14 April). A diversion route will be clearly signposted.<\/p>\n<h2 id=\"m6--junction-1-to-junction-7--resurfacing-works\">M6 \u2013 junction 1 to junction 7:  resurfacing works<\/h2>\n<p>The northbound carriageway will be closed overnight for one night from 9pm 13 April until 6am the following morning (14 April). A diversion route will be clearly signposted.<\/p>\n<h2 id=\"m6--junction-10-to-junction-7-resurfacing-works\">M6 \u2013 junction 10 to junction 7: resurfacing works<\/h2>\n<p>The southbound carriageway will be closed overnight for one night from 9pm 13 April until 6am the following morning (14 April). A diversion route will be clearly signposted.<\/p>\n<h2 id=\"m6--junction-9-entry-slip-road-resurfacing-works\">M6 \u2013 junction 9 entry slip road: resurfacing works<\/h2>\n<p>The southbound entry slip road will be closed overnight for one night from 9pm 13 April until 6am the following morning (14 April). A diversion route will be clearly signposted.<\/p>\n<h3 id=\"m6--junction-10-entry-slip-road-resurfacing-works\">M6 \u2013 junction 10 entry slip road: resurfacing works<\/h3>\n<p>The southbound entry slip road will be closed overnight for one night from 9pm 13 April until 6am the following morning (14 April). A diversion route will be clearly signposted.<\/p>\n<h2 id=\"m6--junction-12-exit-slip-road-electrical-works\">M6 \u2013 junction 12 exit slip road: electrical works<\/h2>\n<p>The northbound exit slip road will be closed overnight for one night from 8pm 14 April until 6am the following morning (15 April). A diversion route will be clearly signposted.<\/p>\n<h2 id=\"m6--junction-7-to-junction-8-and-associated-slip-roads-carriageway-surveys\">M6 \u2013 junction 7 to junction 8 and associated slip roads: carriageway surveys<\/h2>\n<p>The northbound exit slip road will be closed overnight between 9pm and 6am from 14 April until 17 April. A diversion route will be clearly signposted.<\/p>\n<h2 id=\"m6--junction-11-exit-slip-road-barrier-repairs\">M6 \u2013 junction 11 exit slip road: barrier repairs<\/h2>\n<p>The northbound exit slip road will be closed overnight between 9pm and 6am from 14 April until 16 April. A diversion route will be clearly signposted.<\/p>\n<h2 id=\"m69--junction-1-exit-slip-road-resurfacing-works\">M69 \u2013 junction 1 exit slip road: resurfacing works<\/h2>\n<p>The northbound exit slip road will be closed overnight between 8pm and 6am from 12 April until 17 April. A diversion route will be clearly signposted.<\/p>\n<h3 id=\"general-enquiries\">General enquiries<\/h3>\n<p>Members of the public should contact the Highways England customer contact centre on 0300 123 5000.<\/p>\n<h3 id=\"media-enquiries\">Media enquiries<\/h3>\n<p>Journalists should contact the Highways England press office on 0844 693 1448 and use the menu to speak to the most appropriate press officer.<\/p>\n<\/div>\n","protected":false},"excerpt":{"rendered":"<p>Summary of planned new and ongoing road improvements over the coming week.<\/p>\n","protected":false},"author":8,"featured_media":0,"comment_status":"open","ping_status":"open","sticky":false,"template":"","format":"standard","meta":{"footnotes":""},"categories":[13],"tags":[],"_links":{"self":[{"href":"https:\/\/mostafa.openonline.co.uk\/index.php?rest_route=\/wp\/v2\/posts\/69434"}],"collection":[{"href":"https:\/\/mostafa.openonline.co.uk\/index.php?rest_route=\/wp\/v2\/posts"}],"about":[{"href":"https:\/\/mostafa.openonline.co.uk\/index.php?rest_route=\/wp\/v2\/types\/post"}],"author":[{"embeddable":true,"href":"https:\/\/mostafa.openonline.co.uk\/index.php?rest_route=\/wp\/v2\/users\/8"}],"replies":[{"embeddable":true,"href":"https:\/\/mostafa.openonline.co.uk\/index.php?rest_route=%2Fwp%2Fv2%2Fcomments&post=69434"}],"version-history":[{"count":0,"href":"https:\/\/mostafa.openonline.co.uk\/index.php?rest_route=\/wp\/v2\/posts\/69434\/revisions"}],"wp:attachment":[{"href":"https:\/\/mostafa.openonline.co.uk\/index.php?rest_route=%2Fwp%2Fv2%2Fmedia&parent=69434"}],"wp:term":[{"taxonomy":"category","embeddable":true,"href":"https:\/\/mostafa.openonline.co.uk\/index.php?rest_route=%2Fwp%2Fv2%2Fcategories&post=69434"},{"taxonomy":"post_tag","embeddable":true,"href":"https:\/\/mostafa.openonline.co.uk\/index.php?rest_route=%2Fwp%2Fv2%2Ftags&post=69434"}],"curies":[{"name":"wp","href":"https:\/\/api.w.org\/{rel}","templated":true}]}}