Press release: King’s Lynn overhead transmission line application given development consent
The development consent is for an overhead electric line, connecting the proposed King’s Lynn B gas turbine power station to the transmission network.
The decision announced today, follows an examination process by the Planning Inspectorate which met or exceeded all the statutory timescales laid down in the Planning Act 2008.
The application was submitted for consideration on 27 July 2012 and accepted to proceed to examination in accordance with section 55 of the Planning Act 2008, (as amended by the Localism Act 2011), on 21 August 2012.
Following a six month examination during which the public, statutory consultees and interested parties were given the opportunity to give evidence to the Examining Authority, a recommendation was made to the Energy Secretary on 10 October 2013.
Planning Inspectorate’s Chief Executive, Sir Michael Pitt, said.
“A major priority for us over the course of the examination was to ensure that communities who might be affected by this proposal had the opportunity to put forward their views.”
“The examination of the application was completed within the timescales prescribed in the Planning Act and a recommendation made to the Energy Secretary. Today’s decision supports that recommendation.”
The decision, the recommendation made by the Panel to the Secretary of State and the evidence considered by the Examining Authority in reaching its decision, is publicly available on the Planning Portal’s, National Infrastructure projects website.
Ends
Journalists wanting further information should contact the Planning
Inspectorate Press Office, on: 0303 444 5004 or 0303 444 5005 or email:
pressoffice@pins.gsi.gov.uk
Notes to editors:
Follow this application on twitter: @KLBConnection
Notes to editors:
- From April 2012, the relevant Secretary of State became the decision maker on all national infrastructure applications for development consent. At the end of the examination of an application, which will still be completed within a maximum of six months, the Planning Inspectorate will have three months to make a recommendation to the relevant Secretary of State who will then have a further three months to reach their decision.
- The Planning Inspectorate, National Infrastructure Programme of Projects details the proposals which are anticipated to be submitted to the Planning Inspectorate as applications in the coming months.
The process in a snapshot
There are six key stages within the process. The summary below provides examples of when and how people have an opportunity to provide evidence to the Planning Inspectorate.
Pre-application
Key activities:
- Project development / developer’s pre-application consultation and publicity
- Environmental impact assessment preparation and scoping, where required
Public involvement:
- Have their say on the proposal to the developer through their pre application consultation
Acceptance by the Planning Inspectorate on behalf of the Secretary of State
Key activities:
- The Secretary of State has 28 days from the day after receipt to decide whether or not an application should be accepted for examination
Public involvement:
- Details will be posted at the Planning Inspectorate’s website on how to register as an interested party – once an application has been accepted for examination and publicised by the developer
- Opportunity to legally challenge a decision not to accept an application
Pre-examination
Key activities:
- Single Inspector or a Panel of three or more Inspectors appointed
- Preliminary Meeting called and held
- Procedure and timetable set for examination
Public involvement:
- Register to say what you agree or disagree with in the application
- Submit your representation
- View application documents submitted by the developer on the Planning Inspectorate website
- Attend the Preliminary Meeting
- Say how the examination should be conducted
Examination
Key activities:
- A maximum of six months to carry out the examination
Public involvement:
- Submit more detailed comments in writing
- Comment on what other people have said
- Request and attend an open-floor hearing
- If being held, request to speak at open-floor and / or issue specific hearing(s)
- Comment on the local authority’s Local Impact Report – detailing the impact of the scheme on the local area
Decision
Key activities:
- A maximum of three months for Planning Inspectorate to issue a recommendation to the relevant Secretary of State, with a statement of reasons
- The relevant Secretary of State then has a further three months from receiving the recommendation in which to issue the decision
Post decision
Key activities:
- six weeks for any legal challenge
Public involvement:
- opportunity to challenge